Summer 2015: Overall construction starts.
End of 2015: Construction of Welcoming Pavilion begins and is scheduled to open in the Fall of 2016.
Summer 2016: Construction of the three-story wing begins and is projected to be completed by the Fall of 2018.
Fall of 2016: Emergency Department expansion construction begins into the old lobby and is expected to wrap up in the Fall of 2018.